West African Gas Pipeline Company

 Key Milestones
Business Principles
PDF Print E-mail
Article Index
2008-2010
2007
2005-2006
2003-2004
1982-2002

December 2004
Benin, Ghana, Nigeria and Togo pass enabling legislation to establish common framework for the company's operation across four countries; Shareholders take Final Investment Decision (FID)

November 2004
Nigeria Federal Ministry of Environmental issue EIA Permit/Certificate; Benin, Ghana and Togo grant provisional EIA approvals

October 2004
Ratification of WAGP Treaty by the 4 Project countries

January 2004
Final Draft of WAGP Environmental Impact Assessment (EIA) Report submitted to all States, World Bank, OPIC and MIGA

December 2003
Public Notification, Display and Technical Workshops on the WAGP Front End Engineering Design (FEED) Package and Land Acquisition Process in Ghana, Togo and Benin

November 2003
Sensitization Seminar on WAGP, WAGP Treaty, IPA and Enabling Legislation for Joint Parliamentary Committees in Togo

September 2003
Sensitization Seminar on WAGP, WAGP Treaty, IPA and Enabling Legislation for Joint Parliamentary Committees of Benin

May 2003
Signing of International Project Agreement (IPA) by WAPCo and the Government of Benin, Ghana, Nigeria and Togo with ECOWAS Secretariat as Witness

May 2003
Formation of WAPCo to build, own and operate WAGP

April 2003
Conceptual Design Package of Pipeline submitted to the states. (First deliverable in the Pipeline Development plan approval process)

March 2003
Preliminary Draft Environmental Impact Assessment (EIA) Study Report submitted to States, Communities, local authorities, institutional stakeholders and selected key  NGOs.

January 2003
Benin, Ghana, Nigeria and Togo sign West African Gas Pipeline (WAGP) Treaty



 

Quick Navigation



Login Form

Key Milestones

April 2009
Ghana's Volta River Authority generates electricity with natural gas from WAGP
December 2008
First natural gas supply through WAGP arrives in Ghana
October 2008
Hand over of the first of Year One CDP in Togo
August 2008
WAPCo makes 8 million man-hours without a lost time injury
April 2008
Commissioning of onshore and offshore pipeline begins with the opening of valves at Itoki inlet