 Key Milestones
Business Principles

2008-2010

Article Index

January 1 2015

Nigeria Gas Company (NGC) Ltd registered as a shipper

July 1 2012

Pipeline now open to all shippers

March 2011

Commercial Operation Dated declared

February 2011

Compressed gas transport on WAPG fot the first time

January 2011

First natural gas delivered through WAPG for the first time

December 2010

WAPCo Starts full commissioning of WAPG system

August 2010

Volta River Authority recives gas at Tema R&M for the first time'

April 2009

Ghana's Volta River Authority generates electricity with natural gas from WAGP

Key Milestones

April 2009
Ghana's Volta River Authority generates electricity with natural gas from WAGP
December 2008
First natural gas supply through WAGP arrives in Ghana
October 2008
Hand over of the first of Year One CDP in Togo
August 2008
WAPCo makes 8 million man-hours without a lost time injury
April 2008
Commissioning of onshore and offshore pipeline begins with the opening of valves at Itoki inlet