2008-2010

Article Index

August 2006
WAPCo makes 2 million man hours without a lost time injury

August 2006
Construction of WAPCo's Community Development Projects begins

April 2006
Construction of compressor station in Nigeria commences

March 2006
Onshore civil construction begins in Nigeria and Ghana

August 2005
Offshore construction of West Africa Gas Pipeline commences

April 2005
The 4 States give WAPCo Pipeline License to construct pipeline

March-April 2005
Environmental Authorities in Benin, Ghana and Togo grant final EIA Permits

Key Milestones

April 2009
Ghana's Volta River Authority generates electricity with natural gas from WAGP
December 2008
First natural gas supply through WAGP arrives in Ghana
October 2008
Hand over of the first of Year One CDP in Togo
August 2008
WAPCo makes 8 million man-hours without a lost time injury
April 2008
Commissioning of onshore and offshore pipeline begins with the opening of valves at Itoki inlet